Project Brief​

In 2018, ESA was selected as the Engineering, Procurement, and Construction subcontractor to a major utility in Florida to construct a 434.7 kW single tilt carport canopy at the Pelican parking lot on the St. Petersburg Pier.

This solar project is a part of greater scope to renovate the St. Petersburg Pier and revitalize the community with new restaurants, shops, and vendors. The project is a cooperative effort between the City of St. Petersburg, Skanska Construction, RBI and ESA.

As the primary EPC, ESA worked directly with RBI to manage the carport design and construction as well as coordinating with the Utility and the City of St. Petersburg to meet an aggressive construction schedule.

System Details

Location

St. Petersburg, Florida

System Size

435 kW

Installation Type

Carport

Year Completed

2019

Impact

  • St. Petersburg Pier renovation aimed at community revitalization with new restaurants, shops, and vendors
  • Cooperative effort between the City of St. Petersburg, Skanska Construction, RBI, and ESA
  • Coordination between ESA, the Utility, and the City of St. Petersburg to meet an aggressive construction schedule
Project Impact

$1.15 million

Lifetime energy savings

435 kW

Total system capacity

540 metric tons

Carbon Emissions avoided annually

5 months

Implementation Timeline

Case Study Image
Case Study Image
Case Study Image
Case Study Image

We support organizations large and small in bringing energy projects online.

Explore Our Recent Projects

Duke Energy
Advent Health

Get In Touch

Connect with our team to get started.