Project Brief
This Chevrolet dealership in Clearwater, FL partnered with ESA to meet the current energy needs, as well as planning for future energy use from charging upcoming new electric vehicles. By adding 729.96 kW of solar panels, Chevrolet was able to reduce their total electric bill by 84% generating over 3 million dollars in electric bill savings over the next 25 years. This project will generate a 16% IRR, paying the dealership back in just under 6 years.
System Details
Location
Clearwater, FL
System Size
730 kW
Installation Type
Two Rooftops
Impact
- The facility’s total electric bill was reduced by a remarkable 84%.
- The project is estimated to generate over $3.2 million in electric bill savings over the next 25 years.
- The project is expected to generate a 16% Internal Rate of Return (IRR), paying the dealership back in just under 6 years.